Rio de Janeiro, July 29th, 2020 – Vale SA (“Vale”) informs that today it started, on a preventive basis, the Level 1 emergency protocol for Barragem 5, at Mina da Mutuca, Nova Lima (Minas Gerais), a protocol that does not require the evacuation of the population downstream of the dam. This tailings dam was built with compacted soil, with a downstream construction method and no longer receives mining tailings. 

This protocol is a preventive measure and a consequence of the change in technical criteria, with a new interpretation of the resistance parameters carried out by an additional stage of evaluation of Vale's structures in Brazil after the implementation in January of this year of the Engineer of Record (“EoR”) function.

From the most recent inspections, anomalies that could compromise the safety of the structure have not been identified. Barragem 5 had its Stability Condition Statement (“DCE”) issued on March 31, 2020. However, based on the new parameters observed, the DCE will become negative. 

The activation of Level 1 of the dam mentioned in this release does not impact the 2020 production plan, as presented in the Production and Sales Report of 2Q20.


 

Ever since the Covid-19 outbreak began, our highest priority is the health and safety of our employees. Our IR team adopted work-from-home, and as we continue to face these new circumstances, we strongly recommend you prioritize e-mail and online engagement.

For further information, please contact:

Vale.RI@vale.com
Ivan Fadel: ivan.fadel@vale.com
Andre Werner: andre.werner@vale.com
Mariana Rocha: mariana.rocha@vale.com
Samir Bassil: samir.bassil@vale.com

This press release may include statements that present Vale’s expectations about future events or results. All statements, when based upon expectations about the future, involve various risks and uncertainties. Vale cannot guarantee that such statements will prove correct. These risks and uncertainties include factors related to the following: (a) the countries where we operate, especially Brazil and Canada; (b) the global economy; (c) the capital markets; (d) the mining and metals prices and their dependence on global industrial production, which is cyclical by nature; and (e) global competition in the markets in which Vale operates. To obtain further information on factors that may lead to results different from those forecast by Vale, please consult the reports Vale files with the U.S. Securities and Exchange Commission (SEC), the Brazilian Comissão de Valores Mobiliários (CVM) and in particular the factors discussed under “Forward-Looking Statements” and “Risk Factors” in Vale’s annual report on Form 20-F.

​​

Vale informs on Barragem 5