Page 13 - 2017/2018 Annual Update on Vale in Manitoba
P. 13

  Key project milestones:
July 2016 — Project is approved. August 2016 — Mill power line
is relocated.
July 2017 — Foundation work is completed.
January 2018 — Load-Out building is constructed.
April 2018 — New dewatering area is completed. (This includes the thickener and Larox filter press.)
June 29, 2018 — Commissioning is complete and project is handed over to the Mill.
 Concentrate is stored in the load-out facility before it is loaded onto truck and shipped for processing.